LAST PLANNER SYSTEM
How to calculate PPC
Percent Plan Complete shows what share of commitments with a recorded outcome was completed. It helps teams review the reliability of the weekly plan.
01Make Ready review
02Team agreement
03Weekly commitment
04Field outcome
What counts as completed
The work must be complete within the scope and time the team agreed. Partial progress does not fulfill that commitment. Physical progress can be recorded separately.
Whether the next task can start depends on its conditions and dependencies. PPC alone does not determine whether another trade can begin.
Open outcomes and weekly close
This section describes how Promekt's published browser calculator handles entries during the week: it uses commitments with a recorded outcome, completed or not completed. Keep open items in your project record and exclude them from this calculator until you know their outcome. With no evaluated outcomes, it shows no PPC value.
During the week, report how many outcomes still need recording alongside the percentage. At weekly close, review every commitment in the agreed plan and account for items that remain open; leaving them unresolved can produce an incomplete reading. This is product guidance for the published calculation, not a universal LPS definition of PPC.
Keep the original commitment record and subsequent changes. Adding already completed work or removing missed commitments changes the comparison and should be traceable.
How to read the result
| Review | Why |
|---|---|
| Open outcomes | See whether the percentage reflects a full or partial close. |
| Committed scope and workload | Check what work the promises represented. |
| Trend across comparable weeks | Notice changes that deserve review. |
| Recorded reasons and evidence | Understand what happened before agreeing on an action. |
A high PPC does not by itself prove the project is on time or that the workload is appropriate. The result needs context from the plan and execution. The Lean Construction Institute's overview of reliable promises explains how a promise relates to the work and conditions expected by the next activity. It provides context for commitments; it does not define the Promekt calculator's formula.
Review reasons without automatic conclusions
Record the reason for each missed commitment with the person who knows what happened. Materials, equipment, information, predecessor work, or priority changes are prompts for review; a category alone does not prove who failed or what action will solve the issue.
When a reason repeats, review the circumstances and earlier agreements. The team decides what to change, who will own it, and when the outcome will be checked.
Common mistakes to avoid
Confusing tasks with commitments. The calculation starts with promises made for the week, not every row in the schedule.
Closing without verification. Check the outcome with the work owner and available evidence, even if the record is entered from the office.
Using the percentage to rate people. Review work preparation and team decisions without turning the indicator into an accusation.
Calculate your week
The PPC calculator lets you adjust the rows to represent commitments with known outcomes, mark whether they were completed, and review the reasons you select. It requires no account and calculates in your browser.
Review the method with your team
In a demo, we can discuss how these ideas might fit your project's planning.
Request a demo