PPC calculator
01Make Ready review
02Team agreement
03Weekly commitment
04Field outcome
Commitment review
4 promises · 2 completed
50%
PPC for evaluated commitments
The sample starts with four promises: two completed and two missed. Change an outcome or reason to see PPC and the reason breakdown update.
- 1
- 2
- 3
- 4
Recorded reasons
This breakdown shows the reasons entered for missed commitments. Review them with the team before choosing an action.
- Materials1 · 50%
- Predecessor work1 · 50%
The calculation runs in your browser. Your choices are not sent or saved; reloading restores the example.
How to use it
- Adjust the rows to represent commitments already evaluated as completed or not completed. Keep open items in your weekly record; this calculator excludes them.
- Mark which commitments were completed within their agreed scope and time. Partial progress does not fulfill the commitment.
- Choose a recorded reason for each missed commitment. Leave it unclassified if the reason is not known.
- Review PPC and its causes with the team. The calculation is completed ÷ (completed + not completed) × 100; with no closed outcomes there is no value. Recorded reasons support a team review, not an automatic diagnosis.
What it measures and what it does not
PPC shows the reliability of evaluated commitments. Open work is excluded until it has an outcome; resolve it to review the full weekly close. The percentage does not prove physical progress or milestone fulfillment. Also review the committed scope, reasons, and evidence. See how to calculate PPC step by step.
Review PPC alongside the weekly plan
Promekt connects weekly commitment outcomes with recorded reasons. Request a demo to discuss how this could work for your project.