Lookahead: prepare the coming weeks

Lookahead planning gives the team time to review what each task needs. Resolve open conditions before making weekly commitments.

ILLUSTRATIVE DIAGRAM / READINESS
Check conditions before making a promise.Previous work, materials, and crew are marked verified; inspection is pending. After Make Ready review, the work stays in preparation.Previous work✓Materials✓Crew✓InspectionPendingMake Ready reviewStays in preparation

Previous workVerified

MaterialsVerified

CrewVerified

InspectionPending

Make Ready review

Stays in preparation

Check conditions before making a promise.Work stays in preparation when a condition blocks it. Make Ready review precedes commitment.

Choose a useful horizon for your project

Six weeks is the horizon used in this example. Adjust the window to your project's purchasing lead times, requests for information, permits, and predecessor work.

Track longer-lead needs earlier, such as a purchase that takes more than six weeks.

Start from the agreed sequence

Pull Planning establishes production order and dependencies. In Lookahead, teams review upcoming work with a clear location, scope, and responsible people; they do not invent a parallel sequence. The Lean Construction Institute's Last Planner System overview describes how pull planning, make-ready planning, and weekly work planning connect.

Review the conditions

ConditionQuestion for the team
Information and drawingsAre the required decisions available and current?
MaterialsWill they arrive on time and meet requirements?
CrewsWill the trade and capacity be available?
EquipmentHas its availability been confirmed for this work?
Predecessor workAre the dependencies satisfied?
Permits and safetyAre required approvals and conditions verified?

Assign an owner and date to each constraint. Follow its resolution and keep the evidence needed to verify it.

Ready does not mean committed

Closing constraints is necessary, but teams must also verify dependencies, crews, and task requirements. Make Ready governs that check. The weekly plan then records commitments the team agrees to fulfill.

Do not release work with pending conditions just to fill the week. Review other prepared options and address the blocker with its owner.

Learn from the weekly close

PPC records commitment reliability. If materials or predecessor work caused missed commitments, review what was checked during preparation and what changed later.

A percentage or recorded reason is not enough to conclude that Lookahead failed. Compare preparation, changes, and evidence with the team before choosing an improvement.