LAST PLANNER SYSTEM
Lookahead: prepare the coming weeks
Lookahead planning gives the team time to review what each task needs. Resolve open conditions before making weekly commitments.
Previous workVerified
MaterialsVerified
CrewVerified
InspectionPending
Make Ready review
Stays in preparation
Choose a useful horizon for your project
Six weeks is the horizon used in this example. Adjust the window to your project's purchasing lead times, requests for information, permits, and predecessor work.
Track longer-lead needs earlier, such as a purchase that takes more than six weeks.
Start from the agreed sequence
Pull Planning establishes production order and dependencies. In Lookahead, teams review upcoming work with a clear location, scope, and responsible people; they do not invent a parallel sequence. The Lean Construction Institute's Last Planner System overview describes how pull planning, make-ready planning, and weekly work planning connect.
Review the conditions
| Condition | Question for the team |
|---|---|
| Information and drawings | Are the required decisions available and current? |
| Materials | Will they arrive on time and meet requirements? |
| Crews | Will the trade and capacity be available? |
| Equipment | Has its availability been confirmed for this work? |
| Predecessor work | Are the dependencies satisfied? |
| Permits and safety | Are required approvals and conditions verified? |
Assign an owner and date to each constraint. Follow its resolution and keep the evidence needed to verify it.
Ready does not mean committed
Closing constraints is necessary, but teams must also verify dependencies, crews, and task requirements. Make Ready governs that check. The weekly plan then records commitments the team agrees to fulfill.
Do not release work with pending conditions just to fill the week. Review other prepared options and address the blocker with its owner.
Learn from the weekly close
PPC records commitment reliability. If materials or predecessor work caused missed commitments, review what was checked during preparation and what changed later.
A percentage or recorded reason is not enough to conclude that Lookahead failed. Compare preparation, changes, and evidence with the team before choosing an improvement.